4-6 Unpacking and inspecting the EC 11 equipment
Installing the EC 11 cabinet
Standard 1.0 Option 11 EC Installation and Maintenance Guide November 1999
Installing the EC 11 cabinet
Introduction
The procedure for wall mounting an EC 11 cabinet is
identical to the procedure for wall mounting a Meridian 1
Option 11 switch cabinet.
The procedure is not repeated here. Refer to the folllowing
Nortel documents:
• Meridian 1 Option 11—General Information and
Planning Guide (NTP 553–3011–200)
• Meridian 1 Option 11—Installation Guide
(NTP 553–3011–210)
Note 1: Cabling limitations with MGate cards require that
you install the EC 11 no more than 9 meters (30 feet) from
the Meridian 1 Option 11 switch. Regulatory requirements
for some countries may limit this even further to 3 meters
(10 feet), which is the length of the CISPR-B compliant
NTDK3305 NLI cable.
Note 2: You must connect the ground lug on the EC 11
connector panel to the same grounding point used by the
Option 11 switch.