Cutover Migration Task List Example
128
Front-End Regression Test Suite
1 Perform user regression testing.
2 Monitor and capture system dynamics (
sp_who, sp_lock...).
3 Verify and document this regression test.
Other Testing
Verify 12.5 performance and functions on the test system.
Run User/Acceptance Tests on Release 12.5 Test System
1 Testers perform user regression testing of Release 12.5.
2 Monitor and capture system dynamics (
sp_who, sp_lock...).
3 Verify and document the regression test.
4 Make the Release 12.5 “go/no go” decision for the production system.
Execute Fallback Procedures on Test System
1 Shut down the Release 12.5 test system.
2 Recreate the older (current production) release test system.
3 Recreate the older environment, using your recreation scripts and
procedures.
4 Load the older production system dumps.
5Run
dbcc commands (checktable, checkalloc, checkcatalog) on the
older databases. Be sure to verify the
dbcc log and error log.
6Run
checkpoint on the older release test system.
Upgrade Production Server to ASE 12.5
1 Dump the databases on the current production system.
2 Before the upgrade, run
dbcc commands (checktable, checkalloc,
checkcatalog).