APPENDIX B Sample Migration Task Lists
127
3 Make the “go/no go” call for the test system.
4 Verify and document the regression test.
5 Verify performance and functions on the older release test server.
Upgrade Test System to Release 12.5
1 Perform a dump of the current system’s databases.
2 Before the upgrade, run
dbcc commands (checktable, checkalloc,
checkcatalog).
3 Alter the
sybsystemprocs database.
4 Perform a pre-upgrade verification.
5 Upgrade the test system to Release 12.5.
6Run
dbcc commands (checktable, checkalloc, checkcatalog) on the
Release 12.5 databases. Be sure to verify the
dbcc log and error log.
7 “Baseline” the Release 12.5 configuration.
Run Regression Test Suites on Release 12.5 Test System
Recycle server before starting tests.
Back-End Regression Test Suite—Production Loads
1 Iteratively perform the back-end regression testing.
2 Monitor and capture system dynamics (
sp_who, sp_lock, statistics
io
...).
3 Verify and document regression test.
Front-End Simulation Regression Test Suite
1 Perform front-end simulation regression testing.
2 Monitor and capture system dynamics (
sp_who, sp_lock...).
3 Make the “go/no go” call for the 12.5 system.
4 Verify and document this regression test.